Cane Creek Motor Coach ResortIWS' first job in South Carolina! 7,500 GPD wastewater treatment system with 3 Orenco AX-100 Advantex pods, 10,000 gallown recirculation tank, 5,000 gallon wet well and a retention pond.

Location

Cross Hill, South Carolina

Project Scope

Wastewater Treatment

In April 2008, IWS completed construction of a wastewater treatment facility for the Cane Creek Motor Coach Resort in northwest South Carolina.   This was the first commercial AdvanTex treatment system constructed in this region of South Carolina.

The AdvanTex treatment system was designed to handle 7,500 gallons per day.  The system will re-use effluent by irrigating an adjacent field using spray irrigation.  Treatment system components:

  • Three AX-100 Treatment Units
  • 10,000 Gallon Recirculation Tank
  • 5,000 Gallon Wet Well
  • Retention Pond

During the engineering process, IWS provided constructability analysis and materials selection that reduced the cost of the treatment system by more than twenty percent.