HIGHLIGHTS
Installation of 500,000-gallon clear well and 1 MGD filtration system.
Maintained continuous water treatment during construction.
Quickly adapted to unexpected shallow groundwater discovery.
SUSTAINABLE SOLUTIONS MEETS BUDGET CONSTRAINTS
Integrated Water Services (IWS) completed the construction and start-up of the Bayfield Water Treatment Plant Expansion located in southwest Colorado. This project was a partnership between Bayfield, a rural town, and the local La Plata Archuleta Water District to upgrade and expand the existing water treatment plant to serve the town and surrounding areas.
The work encompassed:
Demolition
Upgrades to intake facilities
Modifications to the existing building
Construction of a new plant
All of this was achieved while maintaining the continuous operation of the existing facility.
CHALLENGES FACED
SOLUTIONS IMPLEMENTED
OUTCOME AND IMPACT
The Bayfield Water Treatment Plant Expansion was a successful critical infrastructure upgrade for the town of Bayfield. The project team skillfully managed complex construction, which included a 500,000-gallon clearwell. By collaborating closely and mobilizing rapidly, they overcame the challenge of unexpected shallow groundwater and achieved an on-time completion, all without interrupting the existing plant’s operation.
“IWS did a great job in maintaining the schedule and staying ahead of the constructability issues, which included unanticipated dewatering for the main excavation. I would highly recommend IWS for future projects.” Ron Saba, Town of Bayfield Public Works Director.
For more information, please click here to Contact Our Experts.