Central California Coast Winery

PROJECT TYPE: Wineries
SERVICE: Construction
TECHNOLOGY: Textile Filter
SUSTAINABLE / WATER RE-USE: Spray Field, Landscape/Subsurface Irrigation

A partial view of the spray field area

The completed AdvanTex treatment system installed at or below grade

Tanks installed in excavation

Extensive earth work was required to set the tanks at the correct elevation

The Presqu’ile Winery vineyards

LOCATION: Santa Maria Valley, CA
DESCRIPTION: IWS constructed the first Orenco Advantex project on the California Central Coast to treat winery process wastewater. The treatment train includes the following: a) three,
4,000 gallon settling tanks; b) one, 4,000 gallon recirculation tank; c) one, 25,000 gallon effluent tank; d) six Advantex AX-100 treatment units; and e) a spray field for dispersal.

IWS was able to mobilize with the proper resources to get the system installed so the other trades could move in and keep the project on track

Located in the Santa Maria Valley on California’s Central Coast, the Presqu’ile Winery (www.presquilewine.com) is constructing a permanent winery and tasting room which required a wastewater treatment system for its process water from wine making operations. The winery includes 73 acres of certified sustainably farmed vineyards on the 200 acre site where they produce Santa Maria Valley Pinot Noir, Chardonnay, Syrah, and Sauvignon Blanc.The treatment system was designed by Summit Engineering, Inc.(www.summit-sr.com) of Santa Rosa, CA and can accommodate the production of up to 25,000 cases of wine per year. The process wastewater includes all aspects of wine making from crush through the fermentation and bottling process. This is the first Orenco Advantex project on the California Central Coast to treat winery process wastewater. The treatment train includes the following: a) three, 4,000 gallon settling tanks; b) one, 4,000 gallon recirculation tank; c) one, 25,000 gallon effluent tank; d) six Advantex AX-100 treatment units; and e) a spray field for dispersal.

The treatment system installation was designed with a small footprint so as to accommodate the various landscaping and parking lot features for the facility. As a result, the system excavation was fairly deep and required extensive earth moving to step back the excavation and set the tanks. The layout included placing the Advantex Pods on bedded gravel on top of the fiberglass tanks.

 

The treated process wastewater is dispersed in a 1.25 acre spray field located approximately 300 feet from the treatment system. The spray field area is covered with native plants and grasses to maintain the natural setting of the area.

Richard Ross, Project Engineer for Summit Engineering, designed the system and oversaw the construction. Richard provided his perspective, “We were very pleased with the IWS team and their responsiveness. They did an excellent job of communicating back to the engineer and general
contractor.”

IWS was part of the construction team under contract with the General Contractor, Cello & Maudru Construction (www.cello-maudru.com). Cello & Maudru needed IWS to mobilize to the site first and get the wastewater infrastructure in place before the other trades could begin their work, which put the IWS scope of work in the critical path of the project. IWS was able to complete construction within 60 days of contract execution.

Doug Pedersen, Project Manager for Cello & Maudru commented on the IWS project execution: “IWS was able to mobilize with the proper resources to get the system installed so the other trades could move in and keep the project on track. We were impressed with their professionalism and cooperation as part of the construction team to deliver on the schedule and cost”.

For more information, please click the ‘Contact’ tab to reach out to us.

IWS Central California Coast Winery

Download PDF