Home » California Community Achieves Title 22 Water Re-use Milestone with MBR

California Community Achieves Title 22 Water Re-use Milestone with MBR

March 4, 2020 Case Studies

The community of Monte Verdi Estates in Clovis, CA has upgraded it’s existing SBR wastewater treatment system to an MBR treatment system to meet its Title 22 Re-Use discharge limits, thereby allowing the use of the recycled water to irrigate the greenbelt areas throughout its subdivision versus using potable water for irrigation.

This 125 home development located just outside the City of Fresno, CA was unable to meet its Title 22 requirements with its existing SBR wastewater treatment system for the past 10 years. The new treatment system is a win for water re-use advocates and the community.

Integrated Water Services, Inc. (IWS) was awarded this $4mm upgrade project which included the rental of one of the IWS MBR skid mounted treatment systems to bypass the existing plant during the 6 month upgrade. The plant needed to continue to process wastewater from the community, so the temporary plant was mobilized and flows were diverted to it while the existing plant was taken out of service and upgraded. The average flow rate for the treatment system was 60,000 gpd with peak flow of up to 80,000 gpd of domestic wastewater.

IWS performed all the mechanical, civil, and electrical/controls work on the project. The construction scope of work included: structural and mechanical modifications to the existing building; a new building addition/extension; structural and mechanical modifications to the existing treatment basins; installation of a new Membrane Bioreactor (MBR); and demolition of the existing Sequencing Batch Reactor, sand filters, and associated pumps and piping.

Components of the new MBR facility included: fine screens housed in the new building addition; relocation of the existing grinder and influent flow meter; two new Return Activated Sludge/Waste pumps; two flat plate submerged membrane units; three pre-aeration and membrane blowers; two permeate pumps; new electrical and SCADA systems; repair and reconstruction of existing improvements affected by the work; and all incidentals and appurtenances for a complete and use-able facility. IWS provided treatment plant start-up, testing, commissioning and close-out.

Monty Dill (the owner of Water Dynamics and licensed wastewater plant operator) was contracted to operate the temporary MBR system during the bypass operation said, “The IWS MBR rental unit was well maintained and operated great during the 6 month bypass operation. In addition, we were able to immediately generate high quality effluent with the MBR. I have enjoyed working with IWS and would be glad to partner up with them again in the future. The IWS MBR Rental plant was able to perform normally within 5 days of seed material being introduced.”

Have inquiries about our water or wastewater treatment solutions?
Please click here to Contact Our Experts

 

California Community Achieves Title 22 Water Re-use Milestone with MBR

Download PDF

Sign up for the Integrated Water Services newsletter. 

We share important perspectives and news on MBR wastewater treatment every two weeks.

    Please see our Privacy Policy regarding how we will handle this information.
    Thank you!